Solution Solution

Solution

Selection of high-quality tires from the world

Temporary Tunnel Support Solutions

Engineering Ground Problems Encountered During Tunnel Excavation

As excavation proceeds, temporary support must react to the condition of the ground as it becomes exposed. Installation time can be limited, and geological conditions may evolve from round to round.

Examples:

  • Loose/fractured rock following excavation
  • Unstable roof/crown/sidewall
  • Spalling/ravelling of rock between bolts
  • Overbreak/Blast damaged rock
  • Weak layers/Faults/Shear zones
  • Ground condition variations along tunnel alignment
  • Stress redistribution due to excavation
  • Limited stand-up time in weak ground
  • Squeezing/time dependent deformation
  • Water inflow/Unstable boreholes
  • Variable borehole diameter
  • Limited working space at tunnel face
  • Rapid installation required for support
  • Interaction with drilling/mucking/ventilation activities
  • Damage from blasting/mobile plant
  • Transition from temporary to permanent support
  • Uncertainty if initial support will be “left in”
  • Corrosion if construction period is lengthy
  • Inspection/replacement of damaged support
  • Safe access during installation of support

The anticipated ground conditions should be reviewed continually as tunnel excavation progresses. The support solution implemented for one tunnel reach should not be assumed to be appropriate for another zone with a different geological condition.

 

Our Temporary Support Approach

Wanfeng provides reinforcement and surface-retention components that can be part of a system designed as initial support for a project.

Rock bolts, threaded bars and friction bolts are used to reinforce or restrain rock surrounding an excavation. Bearing plates and steel straps are used to help transfer and distribute applied loads on the surface. Welded wire mesh is used to help retain smaller loose fragments between bolts or other points of restraint.

Components may be used in conjunction with:

  • Scaling
  • Shotcrete
  • Steel sets
  • Lattice girders
  • Forepoling/spiles
  • Pipe- roof systems
  • Face reinforcement
  • Drainage
  • Temporary invert closure
  • Monitoring instrumentation
  • Permanent tunnel lining

Related systems may only be referred to as Wanfeng products when confirmed available for supply by Wanfeng.

Functions of a Temporary Support System

An engineered system of temporary support components can be designed to:

  • Stabilize exposed rock
  • Reinforce fractures and other discontinuities
  • Restrain loose rock between bolts
  • Help distribute localized loads
  • Limit further loosening around the excavation
  • Support the planned excavation sequence
  • Provide protection until installation of subsequent support
  • Provide continued access for personnel and equipment
  • Allow for inspection, testing and replacement
  • Provide traceable components for construction records

TEMPORARY DOES NOT EQUAL UNCONTROLLED

Just because a support component is defined as temporary does not mean it will be replaced quickly. Depending on the construction sequencing, a temporary support can stay in place for weeks or months. It should meet the specified mechanical, dimensional, installation and durability requirements for its actual lifespan.

Component specifications should not be compromised just because they are part of what could be defined as a temporary support system.

Engineering Judgment Disclaimer

The final support type, timing of installation, allowable unsupported advance, bolt pattern and length, anchorage, mesh configuration, shotcrete thickness, excavation sequence and instrumentation should be designed or reviewed by qualified geotechnical, tunnelling, mining and structural engineers. Wanfeng will only supply components specified on approved drawings and is not responsible for determining when an excavation is safe to enter or if temporary support is enough for the tunnel being constructed.

 

Recommended Products

Note that each of these products can have proprietary options or have additional trade names assigned by different manufacturers. Each product category includes examples of key specification fields and common additional fields that should be considered during product selection.

1.Rock Bolts

Steel bolts that can be installed around the tunnel crown, shoulders and sidewalls throughout excavation.

Key specification fields

  • Diameter
  • Length
  • Steel grade
  • Yield and ultimate load

Additional fields

  • Thread profile
  • Anchorage method
  • Threaded length
  • Surface treatment

2.Friction bolts / Split Sets

Friction type bolts that are designed to be quickly installed where the borehole and ground condition are appropriate for the system installed.

Key specification fields

  • Tube diameter
  • Bolt length
  • Steel grade
  • Nominal load capacity

Additional fields

  • Ring configuration
  • Recommended borehole range
  • Surface treatment
  • Installation equipment requirements

Application note

Verification of friction-bolt performance should be accomplished through controlled installation and test loading as specified on the project drawings.

3.Fully Grouted Threaded Rebar Bolts

Steel bars with threads along the full length or defined lengths that can be grouted with cementitious material or resin.

Key specification fields

  • Bar diameter
  • Bar length
  • Yield strength
  • Ultimate tensile load

Additional fields

  • Thread direction/pitch
  • Coupler compatibility
  • Grout or resin arrangement
  • Corrosion-protected option

4.Cable bolts

Longlength steel elements designed for reinforcement where potential instability may exceed the capacity of conventional bolts.

Key specification fields

  • Cable diameter
  • Cable length
  • Strand configuration
  • Minimum breaking load

Additional fields

  • Bulb configuration
  • Grout arrangement
  • Bond length
  • Corrosion protection

Application note

Longlengeth cables are not necessarily required for temporary ground support applications. Their use should be fully justified by means of an approved ground-support design.

5.Bearing plates

Steel plates that are generally used to help transfer load from compatible bolts to the rock surface.

Key specification fields

  • Plate dimensions
  • Plate thickness
  • Hole diameter
  • Steel grade

Additional fields

  • Flat or domed profile
  • Rated load or deformation capability
  • Washer arrangement
  • Surface treatment

6.Welded wire mesh

Panel type product used to restrain smaller loose fragments between active reinforcement locations.

Key specification fields

  • Wire diameter
  • Mesh aperture
  • Panel dimensions
  • Weld strength

Additional fields

  • Edge- wire configuration
  • Recommended overlap
  • Finish (galvanized/zinc-plated or bare)
  • Compatibility with plates and straps

Application note

Mesh strength, fastener capacity, panel overlap and distance from rock surface should be confirmed in the approved support drawing and installation sequence.

7.Steel straps

Flat or profile steel elements used to help support fractured rock masses or to distribute support reaction between bolt locations.

Key specification fields

  • Width
  • Thickness
  • Length
  • Hole spacing

Additional fields

  • Strap profile
  • Hole diameter
  • Steel grade
  • Surface treatment

8.Nuts, Couplers and accessories

Steel elements used with compatible bolts and installed using approved equipment and procedures.

Key specification fields

  • Thread type and size
  • Nut or coupler dimensions
  • Steel grade
  • Surface treatment

Available configurations may include some or all of the following:

  • Nuts
  • Couplers
  • Washers
  • Centralizers
  • Spacers
  • Installation accessories

 

Temporary Tunnel Support Selection Matrix

Typical excavation or ground condition Typical support requirement Product categories or systems that may be relevant
Competent rock with isolated loose blocks Localized reinforcement Rock bolts with bearing plates
Jointed crown or sidewalls Reinforcement across discontinuities Rock bolts or threaded bolts
Fractured surface rock Reinforcement and surface retention Bolts with welded wire mesh
Small fragments between bolt positions Continuous surface retention Mesh with suitable plates and fasteners
Blocky ground or intersecting joints Load distribution between bolts Bolts, mesh and steel straps
Rapid drill-and-blast cycle Timely installation after scaling Approved rapid-installation bolts with mesh where required
Variable but stable boreholes Installation system compatible with measured hole variation Only bolt systems verified for the specified borehole range
Collapsing or water-bearing holes Anchorage suitable for poor hole conditions Project-designed grouted, cased or alternative system
Fault or shear zone More continuous initial support Fully grouted bolts, mesh, straps and shotcrete as designed
Weak ground with short stand-up time Support installed close to the excavation face Project-designed pre-support, shotcrete, bolts, ribs or closed support ring
Local deep instability Reinforcement beyond the shallow loosened zone Longer threaded bolts or cable bolts where verified
Temporary wet environment Construction-period corrosion resistance Galvanized, coated or otherwise protected components
Squeezing or deforming ground Controlled deformation capacity Only verified yielding or deformable products in an engineered system
Dynamic or seismic demand Verified energy absorption Only products supported by relevant dynamic test data
Initial support intended to contribute to final support Documented structural and durability performance Products specifically assessed for permanent design requirements

Selection Disclaimer

The following matrix should be used as a preliminary guide only. The following products or systems may be appropriate for certain conditions and are not to be considered a recommendation for all applications.

Support type, unsupported advance, installation distance from face, bolt spacing, anchorage, shotcrete and testing should be determined by site-specific engineering.

 

Temporary Support and Permanent Support

Temporary support and permanent support should be clearly distinguished in project documents.

Design consideration Temporary or initial support Permanent support
Primary purpose Stabilize the excavation during construction Meet the specified long-term structural and service requirements
Exposure period Construction period or defined temporary duration Full design life
Design basis Construction-stage ground loads and sequence Long-term loads, durability and serviceability
Corrosion protection Based on actual temporary exposure Based on groundwater, environment and design life
Inspection Frequent construction-stage inspection Planned long-term inspection and maintenance
Structural contribution Not automatically included in final design Included only where explicitly designed and verified
Removal Only under an approved sequence Normally remains as part of the completed works
Documentation Installation and construction records Permanent works records and compliance documents

Design Note

Permanent status should not be assumed for initial support.

Prior to designing temporary bolts, mesh, shotcrete or other means of support as part of the permanent load-resisting system, the project engineer should confirm that:

  • Acceptable long-term mechanical performance
  • Corrosion protection
  • Deformation compatibility
  • Material durability
  • Load sharing assumptions
  • Interface with final lining
  • Construction inspection limitations
  • Design standards
  • Installation quality has been documented.

Short-term performance criteria do not ensure permanent acceptability.

 

Customizing Products for Temporary Support Applications

Wanfeng can evaluate product schedules and approved drawings for custom manufacturing capability.

These attributes are candidates for customization:

  • Diameter of bolt or bar
  • Overall length
  • Thread profile, direction and pitch
  • Threaded length
  • Steel grade
  • Mechanical properties
  • Friction-bolt tube diameter
  • Bearing plate length, width, and thickness
  • Plate profile and hole diameter
  • Mesh wire diameter
  • Mesh aperture and panel size
  • Steel strap profile and hole spacing
  • Nut and coupler configuration
  • Hot-dip galvanizing or other coating specification
  • Product marking
  • Batch marking
  • Bundle quantity
  • Packaging for installation sequence
  • Inspection and test reports

All customization requirements should be confirmed on an approved drawing, product schedule or technical agreement prior to manufacturing.

 

Production and Quality Assurance Guidelines

Inspection criteria should be commensurate with material type, project specification and mutually agreed inspection protocol.

1.Raw Material Inspection

  • Review of mill test certificates
  • Confirmation of steel grade
  • Heat-number identification
  • Verification of chemical composition, if required
  • Checking of material dimensions
  • Visual inspection of surfaces

2.Dimensional and Thread Inspection

  • Verification of outside diameter and length
  • Straightness, if required
  • Profile of tube
  • Thread profile and pitch
  • Verification of threaded-length
  • Plate thickness and hole size
  • Strap dimension and hole-spacing
  • Mesh aperture and panel dimension
  • Nut and coupler fit

3.Mechanical Property Testing and Mechanical Testing

  • Yield testing, if required
  • Tensile Strength testing, if required
  • Elongation, if required
  • Bolt or bar tensile testing, if required
  • Friction-bolt component testing, if required
  • Nut and coupler load resistance testing, if required
  • Bearing plate load or deformation testing, if required
  • Mesh weld shear resistance testing, if required
  • Sample or batch testing, if required by project specifications

4.Weld Inspections

  • Weld position
  • Uniformity of weld
  • Visual inspection of incomplete or damaged welds
  • Mesh uniformity
  • Weld shear strength testing, if required

5. Surface Coating Controls

  • Surface prep requirements
  • Coating thickness, if required
  • Coating coverage and general appearance
  • Thread-fit, if threads are coated
  • Protection of mating threads or surfaces
  • Packaging requirements for coated items

6. Marking, Identification and Final Inspection

  • Heat number or batch number identification
  • Marking of finished product
  • Review of inspection results
  • Quantity verification
  • Review of drawing and purchase order
  • Packaging
  • Review of shipping documentation

7. Certificates

  • Certificate/report number
  • Issuing company
  • manufacturing facility
  • Item(s) tested
  • Test property
  • Standard referenced
  • Dates of issue & Validity
  • Format: Download PDF Report

List standards such as ASTM, EN, ISO, AS/NZS or others only if conformity can be assured for the product being supplied and the project requirements.

 

Installation, Inspection and Replacement

Performance of temporary support is reliant on the entire installation and inspection regimen being completed.

The approved project plan may include:

  • Inspection/scaling prior to support installation
  • Maximum allowable unsupported advance
  • Location for workers to safely stand while installing supports
  • Distance away from face to install supports
  • Borehole alignment, position and depth
  • Borehole diameter and condition
  • Requirements for cleaning holes
  • Grout or resin
  • Required bolt torque/preload
  • Plate seating onto rock surface
  • Mesh overlap and fastening
  • Strap position/connection
  • Shotcrete interface
  • Record-keeping during installation
  • Pull, torque or other method of verification testing
  • Inspection after blasting
  • Inspection before beginning each shift
  • Inspection when water inflow or ground movement occurs
  • Recognition of damaged or misplaced support
  • Safe method of replacement
  • Timing of replacement in relation to permanent support
  • Approval required prior to removal of temporary support.

Replacement Warning

Damaged or misplaced support should be identified and corrected in a timely manner following the approved ground-control procedure. Sequence of replacement should be considered and should never leave workers unprotected and exposed to unsupported ground.

Wanfeng does not define the safe removal sequence of installed tunnel support.

 

FAQ

1.What is temporary tunnel support?

Answer:Temporary support is installed during excavation as needed to stabilize exposed ground and/or provide safe construction access prior to installation of subsequent or permanent support. Examples include bolts, mesh, straps, shotcrete, ribs, etc.

2. Common products used for initial tunnel support?

Answer:Rock bolts, friction bolts, threaded bars, bearing plates, welded wire mesh, steel straps and compatible accessories are commonly used, depending on ground and excavation conditions. The complete system should be defined by the project engineer.

3. How soon should temporary support be installed?

Answer:This will vary based on ground stand-up time, sequence of excavation and requirements of the approved ground-support plan. Wanfeng cannot provide a general recommendation for safe distance or unsupported period that will apply in all situations.

4. Are friction bolts ever used as temporary support?

Answer: Friction bolts can be appropriate where borehole diameter, rock condition, applied load and expected construction duration are suitable for the product being considered. Installation procedure and performance should be confirmed for project conditions.

5. How do bolts and mesh work together?

Answer: Bolts are used to reinforce/restrain the rock mass and provide attachment points at the surface of the excavation. Mesh is used to retain smaller fragments between bolts, and plates/straps may help distribute loads and secure the mesh to the rock.

6. Can temporary support be part of the permanent design?

Answer: Only if its contribution to overall structure, installation quality, durability, corrosion protection and interaction with the final lining have been evaluated and accepted by the project engineer.

7. Does temporary support need corrosion protection?

Answer:Yes, depending on exposure to water, chemicals, anticipated lifetime and whether the materials will remain in place. “Temporary” does not automatically mean ” unprotected”.

8. What should be done if temporary support is damaged?

Answer:Support that is damaged or displaced during construction should be inspected and repaired/replaced as part of the approved ground-control procedure. Load-carrying support should not be removed by personnel unless an engineered sequence and appropriate protection have been designed.

Products
Contacts
WhatsApp
Email